Completion report One Beverly April 2025
Arjan, Dubai
A home where style, comfort, and energy come together as one.
📍 Project Overview
Construction Start: January 2025
Estimated Completion: Q1 2027
Current Stage: Above-ground structure underway




Excavation & Foundation
January 2025
- Excavation and Cart away more than 49,000 m – Complete
- Foundation preparation and leveling more than 4,000 m of block used – Complete
Raft Foundation Casting
March 2025
-
8,000 M of concrete has been poured over 80 Man hours working – Complete






Retaining Wall & Basement
March 2025
Retaining wall & Basement Verticals 100% – Complete
Ground Floor & 1st Floor
April 2025
-
Ground floor casting more than 75% IN PROCESS
-
Vertical of 1st Floor slab are in progress 40% IN PROCESS




One Beverly isn’t just real estate — it’s where new beginnings are built without limits.
We’re committed to transparency at every step. Watch your future home come to life through regular updates and milestones.