Completion report One Beverly April 2025

Arjan, Dubai
A home where style, comfort, and energy come together as one.

📍 Project Overview

Construction Start: January 2025
Estimated Completion: Q1 2027
Current Stage: Above-ground structure underway

Excavation & Foundation

January 2025

  1. Excavation and Cart away more than 49,000 m – Complete
  2. Foundation preparation and leveling more than 4,000 m of block used – Complete

Raft Foundation Casting

March 2025

  1. 8,000 M of concrete has been poured over 80 Man hours working – Complete

Retaining Wall & Basement

March 2025

Retaining wall & Basement Verticals 100% – Complete

Ground Floor & 1st Floor

April 2025

  1. Ground floor casting more than 75% IN PROCESS

  2. Vertical of 1st Floor slab are in progress 40% IN PROCESS

One Beverly isn’t just real estate — it’s where new beginnings are built without limits.

We’re committed to transparency at every step. Watch your future home come to life through regular updates and milestones.

Exclusive Agent Access Starts Here

Join us to learn more about projects and be the first to receive exclusive updates and availability